Electron Cooling Goals:
Present
Goals:
Cool 600e10 Pbars in Recycler.
Completed Goals:
02/28/05 - All Ecool systems are ready for commissioning.
03/14/05 – Beam is transported to the collector through U-bend.
04/04/05 - Beam is transported through the cooling section.
07/08/05 (proposed date) - 0.5 amp DC beam established on July 26, 2005.
09/08/05 (proposed date) – First cooling of 8.9 GeV antiprotons achieved the week of July 18, 2005.